Tuesday, June 30, 2009

IEM Southern Branch Talk on the 27 June 2009




On Saturday 27th June 2009, I was invited by the IEM Southern Branch, Johor Baru to deliver a Talk during their AGM at the Persada Convention Centre. The title of my Talk was Cost Effective Steelwork Design for Fabrication. The talk was attended by over 100 participants of which most of the are Engineers. IEM President, Datuk Prof Ir Chuah was also present as an observer for the Southern Branch AGM. I was quite pleased with the turnout and also the positive feedback given by the participants on the talk proper. The contents of my talk is included here in my previous post.




















Friday, January 2, 2009

Cost Effective Steelwork Design for Fabrication

Introduction
Structural Steel is still a relatively new material to be used entirely in the design and construction of buildings in Malaysia. This is in contrast to Europe and America, where steel structures is utilized in most of their new structures whether it is for public or commercial uses. Over here steel structures is predominantly limited to factories, manufacturing plants and industrial plants etc.

Over the past 15 years, the cost of steel sections in Malaysia has increased dramatically. The rise of Perwaja Steel in the mid 90’s to overcome cost and shortage of structural sections did little to spruce up the steel consumption locally and hence led to its closure of the structural sections mill in the turn of the century.

With rising cost in raw material and labour, it is evident that cost effective design, detailing, low weight (to a certain extent) and buildability concept should be employed to achieve an overall economic advantage.
Low weight structures should not be confused with least weight structural solutions which very rarely produce the most cost effective designs as generally low weight structures are more labour intensive per tonnage weight.

This technical note are compiled from recommendations driven by the steel industry’s which educates designer’s on buildability and detailing issues which subsequently reduce fabrication cost.

Preferred concept for structural form
Some of the basic ‘ideals’ which will encourage economical solutions are as follows:

1) Structure should be a ‘braced’ where possible rather than an ‘unbraced’ structural frame. Lateral loads should be resisted via a stiff vertical braced element.
2) The arrangement of structural members should be on a regular, orthogonal grid for direct load path and also to give maximum component repetition.
3) Economic steel weight solutions in many buildings can be achieved by composite floor construction.
4) The maximum size and weight of member should be commensurate with the site logistic, transportation and cranage available.

During the conception of structural solutions options, an overall compromise has to be reached which recognizes the interaction between related cost areas, and unless this process is extended from material specifications to fabrication and site erection, cost perception may become distorted.

Connection Design and Detailing
Steelwork connections and detailing attribute almost 30% of the cost of typical frames. Connections details are largely dictated by the design concept which is the key factor in determining how the structure will be made, how it will be transported, and how it will be assembled on site. Therefore, it is imperative that designers have a good rounded knowledge of all aspect of steel construction during the preliminary design stage as design in isolation will risk an adverse cost penalty.

In the early 90’s, the Steel Construction Institute in UK have produced design and detailing recommendations for simple steelwork connections. These have now been accepted as the UK industry standard. As a matter of fact, we should adopt these as our own as they are highly versatile and simple in their approach to connections design and detailing. The major benefits of these guide includes:

- rationalization of the different types of connection to those which are compatible
with modern fabrication process and erection methods
- promotion of standard wide flats and angles for fitting and M20 8.8 fully threaded bolts throughout. (thereby improving the efficiency of stock control and purchasing)
- holes in fittings should where possible be punched and welds comprise of single pass fillets (thereby streamlining production)
- capacity tables developed for standard details (thereby minimizing the design and detailing effort expended)

Other recommendations that need to consider in addition to the above are:

- keep details simple and repetitive to reduce drawing office and workshop time
- Standardize bolt sizes, pitches and centers (each time a hole diameter is altered, delay results while the drill bit is changed)

Cost of Connections
Cost of connections will vary depending on the fabrication effort required. Many designers are unaware of the relative cost of connections – consequently, the indiscriminate, and unnecessary, specifications of full-strength or fully welded connections are commonplace. Bear in mind, that connections classification for beam to column are either ‘simple’, moderate or complex, where a full moment connections are often classified as ‘complex’ henceforth. The fabrication effort for ‘complex’ connections simply to reduce weight in structural frames is a false economy as the cost for producing ‘complex’ connections far outweighs the weight saved.

Rationalisation of section types
The number of section and grades used in the design should be rationalise so that its benefits can be reaped. The benefits are:

- repetitive details and dimensions
- reduced design and fabrication efforts

In general the feasibility of rationalization is project specific and the followings guidelines will be generally applicable:

i) total weight of any one section types less than 10t should be avoided
ii) sections should be rationalized if the total increase in weight is less than 20%

E.g. preferably, columns section should be spliced at intervals of 3, 6, 9 or 12m. In addition, one should also consider the weight of the column concerned where craneage limitation could dictate the splice locations

Materials Selection
Materials grades should be consistent for all elements. Generally, grade 50 is most cost effective in design. However, steel stockiest do not ordinarily stock grade 50 steel sections. Therefore, where quantities are less than 150t or, where sections are required at short notice, grade 43 steel should be specified. Fittings are generally in Grade 43 steel.

Welding
Welding and weld preparation are among the most cost intensive aspects of steelwork fabrication and erection. The relative cost to a 6mm fillet weld can be in the region of 2 to 15 for a 20mm plate single V-butt.

Very often, welds are over specified, with full penetration butt welds being specified where a partial penetration would suffice or fillet welds being used which are significant larger than the minimum required. However, a small increase in the size of fillet welds can have a disproportionately large effect on cost.

Butt welds involve preparation, which is costly if done manually. Nevertheless, for fillet welds larger than 12mm, butt welds will often provide a more cost effective solution.

If access for welding, and or for the subsequent testing of the weld is impeded, then the cost can also be increase indirectly.

Painting
Elaborate paint specifications arte unnecessary and can add up to 25% onto the fabrication cost which for most structure is an avoidable expense. Experience shows that unpainted steelwork can remain structurally sound, substantiating the case for no protection where the building provides a stable and dry environment. Where priming protection is specified, the function, environment and possible maintenance requirements should be considered in each case rather than adopting a ‘blanket’ philosophy.

Drawings and Specifications
It is imperative that the design intentions are correctly conveyed on contract documentations. This is particularly true where the fabricator doubles up as specialist contractor where they undertake alternative full design or simply connections design only from section sizes and forces supplied by the engineer.
Very often, unnecessary costs accrue from misunderstanding or assumptions made where information has been omitted. The following should be observed as a minimum:

- identify loading sources for force and moment components so that the correct combinations and load factors can be applied in the design. For simplicity the value of the forces can be given in ULS.
- highlight tying forces arising from the integrity requirements in BS5950 (these forces are catered for in isolation and large connection deformation can be assumed in the design)
- provide details of frame philosophy ( highlight lateral stability system)
- identify where the following are required:

HSFG connections
Insitu welding
Moment connections

Onerous requirements for construction tolerances and quality will have an effect on the cost of steelwork. It is advisable to use Standard Specifications such as those produced by the BCSA with SCI i.e National Structural Steelwork Specification should be used.

Do’s and Don’ts Details which Influence Costs

· Use standard flats or structural tee sections for fin plates to SHS bracing members.
· Avoid snipes or rounded corners at the ends of fin plates.
· Use less than 16mm thk plates to avoid through thickness testing
· Avoid stiffening at connections.
· Use standard connections detailing where possible such as those publish by SCI and CIDECT.
· Minimize d/t of chord and maximize d/t for braces ( for CHS and RHS)
· For RHS use either gap or full overlap joints – not partial overlap
· Minimize fabrication effort to allow earliest delivery to site.
· Typically provide splices at three storey intervals or at 6, 9 or 12m height.
· Avoid thin stiffened baseplates, use thick unstiffened baseplates
· Only use ‘all round’ welds to base plates where necessary.
· Avoid changes in serial sizes at splices.
· Avoid web stiffeners, use heavier sections with thicker webs rather than large number of stiffeners
· For maximum efficiency use

Secondary span/Primary Span = 4/3

· Use partial interaction design in composite design whenever possible (reduces number and hence cost of shear connectors)
· Avoid varying spacing and use either single or double rows of shear connectors.

REMEMBER THAT MINIMUM MATERIAL WEIGHT IS NOT NECESSARILY THE LOWEST COST

It will be apparent that a number of these aims will conflict when viewed collectively. For example, reducing the number of different components may be possible only at the expense of more complicated details, and decisions cannot be made in isolation without risking an adverse cost penalty.

The decision of particular emphasis remains a matter of calculated and experience judgment to minimize overall cost, and this will largely depend on the nature and extent of the work.

Key references

Gibbons. C : Economic steelwork design, Technical Note, The Structural Engineer,73, No 15,1 August 1995

Owens, G W and Knowles P R: Steel Designer’s Manual, 5th Edition Oxford Blackwell Scientific, 1992

BCSA and SCI: Joints in Simple Connections: Volume 2: practical applications, London; Ascot: BCSA; SCI, 1993

BCSA and SCI: Joints in Moment Connections: Volume 3: practical applications, London; Ascot: BCSA; SCI, 1993

National Structural Steelwork Specifications for Building Construction 3rd Edition, London: BCSA with SCI 1994

CIDECT Design Guides, Cologne: Verlag TUV, Rheinland

Structural Steelwork and Price Influencing Factors

Introduction
Despite the overall cost competitiveness of steel in construction, many steel framed buildings remain more costly to manufacture and build than they need to be. Details and components often become unnecessarily complicated and expensive because the factors that govern production costs are not always appreciated.

The difference in construction techniques between in situ concrete and steel construction are fundamental to the basic nature of the two materials. Unlike concrete, which is essentially a wet process conducted on site, steel is produced and prefabricated within a controlled environment. This demands prior commitment and close cooperation between members of the design team to ensure that areas of joint responsibility are fully resolved and planned in advance.

Steel fabrication employs production engineering techniques and its success depends on good standardization. Time, and therefore labour , costs can be cut significantly by the repetition of dimensions, geometry, member sizes and shapes, centres and diameters of bolts, etc., all of which are accountable to rationalisation. Further economy is derived by reducing the number of detailed components which tends to be labour intensive even when this results in heavier parent material.

Commercial factors
There is a wide range of factors that influence prices of steelwork apart from the obvious. In general, they can be differentiated between ‘commercial’ and ‘technical’. Some of these include ‘lead times, erection times and typical prices.

Specialist works requires significant confidence and trust between parties involves in the construction (client, engineer, main contractor and steelwork contractor). Normally, with a tried and tested specialist contractor a lower price for the work can be expected as the expectations of mutual parties can often be predicted.

Expertise of the Engineer
A limited amount of consulting engineers are used to designing steel construction projects than others, with resulting simplicity and economy in their designs that will reduce total cost. Specialist steelwork contractors which offer design capabilities can be more economical as their vast experience and exposure to steel can be an added advantage in their designs.

Contract Conditions
Comparatively aggressive terms and conditions will result in higher prices from specialist contractor such as steelwork, which requires significant investment in materials and fabrication processes before any completed works arrives on site. Interim payments such as ‘materials off/on site’ will often lower the overall steelwork cost and improve contingency planning.

Market Conditions
When negotiating with or inviting potential steelworks contractors for a particular project, ascertain how busy they are in terms of their total design, detailing, fabrication and erection capacity when the work is to be placed as this will affect price levels.

Complete Package
Many steelwork contractors offer additional services such as concrete works, fire protection, decking, roofing and cladding. As usual, the larger the project and scope, the greater the economies of scale for price competitiveness.

Site Organisation
A well coordinated site ensures smooth running projects. ‘Congested’ sites in town centre and also remote site necessitate premiums due to transport and logistics. Ensure that the site has adequate access for steel transportation, unloading and erection at the site and adjacent access roads. Ensure that the ground is well prepared and level and is adequate to take the necessary wheel loads. Ensure that pre-site co-ordination is defined and where crane is provided by others it will always be available and in accordance to erection schedule. Ensure that all foundation works are completed within the schedule and anchor bolts set in place within the specified tolerances, free from damage and contamination. All works dependent or associated upon the steelworks needs to be properly identified as to whose responsibilities belies in the supplying and/or installing it.

Technical Factors
These are some ‘technical factors’ which are applicable to most general projects.

Specification
Use Standard Specifications such as those produced by BCSA or SCI to reduce uncertainty or demanding tolerances or testing other than that specified will increase costs.

Frame Grids
Structural steelwork prices are influenced by the number of pieces per tonne, which indirectly relates to the structural scheme or frame grids. Larger grid sizes, increases steel weight due to longer spans may be offset by the reduced price per tonne and also reduced the number of columns and related workmanship. Fewer columns with free column-space generally add value to a project. Lateral stability of frame by stiff core or frame bracing is usually less expensive than rigid or moment frames.

Complexity
Modern CNC fabrication equipment can cope with complex design but in general, the higher the complexity the greater the cost. Fabrication is more economic with:

· Single square cuts
· One hole diameter on any one piece avoids drill bit change
· Holes in flanges and web aligned where possible
· Web holes having adequate flange clearance
· Standardized range of connections
· Most connections are drilled then welded or bolted to the main member.

Where possible, allows the specialist steelwork contractor for alternative steel member selection and also leave the choice of the connections detail to them as the type, range of sections and design of connections directly influences the total frame cost. Design rationalisation of range and tonnages of section sized used is better off left to the steelwork contactor as they have first hand information on stocks, supply, fabrications and erection capability.

Complex individualistic designs are going to cost more per tonne even with modern CNC equipment. KEEP IT SIMPLE – if you wish to keep cost down.

Materials
Steel grades should not be mixed and where possible, rationalise the range of sections sizes/tonnages used in order to minimize cost, lead times and shop handling. In general steel grades S275 are adequate unless the strength requirements of S355 are paramount

Ensure that sections used are appropriate for its particular functions. ‘I’ sections are economical for conventional framing while tubes are good for trusses and to a certain extent for columns. Tubes have a lower gross weight required to perform the same function and also more aesthecally pleasing. Plate is usually used for Built-Up sections and in connections, stiffeners and base plate.

Architectural Requirements
Unnecessary finishing should be avoided and ensure that corrosion paints specifications is appropriate for the environmental conditions to be encountered. Grinding of welds is usually only required for exposed structure in close proximity to the human eye.

Quality of Drawings and Documentation
Accuracy, completeness, legibility and clarity of information are vital for a steelwork contractor to be able to examine the work involved. Where the steelworks are pre-designed, ensure that all member sizes are shown and that the connections forces are shown or are available.

Lead Times
The information that specifiers really need to understand is the elapse time from placing an order to the time of start of delivery of steelwork to site and commencement of erection. This data will varies depending on the complexity of the project but for a relatively straightforward project the period from receipt of order with full information to start of delivery can be typically around 6 to 8 weeks. Similarly erection times can vary depending on location and complexity of project, but normally are around 300 – 500 tonnes per month using one or two cranes.

References

Steel Construction News: ‘Factors Influencing steelwork Prices’: Issue No 10: Dec 2001: BCSA CORUS

R Taggart: Structural steelwork Fabrication: The Structural Engineer: Volume 64A:No.8: August 1986

National Structural Steelwork Specifications for Building Construction 3rd Edition, London: BCSA with SCI 1994